Main photo left: A flood tops the Waitaki dam earlier this
year. Main photo right: Trestle bridges and a coffer dam
stretch across the river 1929-30. Smaller photos clockwise
from top left: Project engineer R.H. Packwood, Lord
Bledisloe (left) and Public Works Minister John Bitchener
in 1934. Crossing the river by punt in 1928. Workers'
housing. The powerhouse under construction. Pick and shovel
workers. Work on a turbine housing. Photos courtesy
Meridian Energy, Otago Witness, David Bruce.
Happy birthday - the Waitaki dam celebrates its 75th
anniversary at Labour Day weekend. David Bruce looks at its
history, its future and some of the people who worked
there.
Using picks and shovels, a construction force of between 1000
and 1200 workers started building the Waitaki dam and its
powerhouse in 1928 - never envisaging it would be the first
of eight that would tame the mighty Waitaki River for
electricity.
• Cold, dam cold
During the Depression, the project provided much-needed work
for those without jobs, although they had to labour through
extremes in a climate ranging from hot summers to
freezing-cold winters.
The Waitaki River had been identified as the best South
Island river for hydro development and field investigations
began in 1925.
Various sites were looked at for the Waitaki dam, one near
Awakino being selected because of good rock foundations at
each abutment and across the valley.
Room was available for a dam and its associated powerhouse
and a railway line as far as Kurow was also an advantage.
The design and construction was handed over to the
Government's Public Works Department hydro-electric branch.
Before construction began, one of the first tasks was to
erect a temporary camp to house up to 1000 workers and their
families.
On past public works jobs, accommodation had been in tents,
but because of the climatic extremes and long-term nature of
the project, it was decided to provide more substantial
wooden houses and huts.
Senior staff were allocated houses built of concrete blocks,
which would remain for permanent staff.
Some of these survive today in the Lake Waitaki Village, now
privately owned.
Main photo left: One of the turbine moulds is reconstructed
in situ in the dam. Main photo right: The powerhouse (at
top) nears completion. Smaller photos clockwise from top
left: In the powerhouse at the opening of the Waitaki dam
on October 27, 1934. Workers pour concrete during
construction of the Waitaki dam and powerhouse. The opening
of the Waitaki dam. A crane lifts one of the Francis
turbines into position in 1932. Photos by Courtesy Meridian
Energy, Otago Witness, ODT Files.
The Kurow railway line was extended to the site, ending a
little downstream of the dam.
Several roads had to be realigned and fenced.
The department had a core permanent works staff, but still
needed a lot of extra people to build the dam.
With the Depression starting to bite, they came from
backgrounds not used to the physical work - unemployed
barbers, musicians, artists, tailors and factory workers.
Many struggled to cope with the physical demands.
A temporary tent camp also developed, accommodating people
waiting to get jobs when vacancies became available.
Numbers working on the project at any one time varied from
1000 to 1230.
Work started in 1928 when a trestle bridge was put across the
river at the dam site.
Instead of the more modern practice of diverting the river
through a tunnel, the dam was built in sections, of about
15m, with those sections under construction protected by a
coffer dam while foundations were anchored to solid rock.
The first coffer dam - which enclosed the area under
construction to provide a dry work environment - enclosed a
short length in the centre of the river, where workers set to
with shovels digging out the foundation.
The river was large, swift and, especially in winter, very
cold.
The wind down the valley could be very strong and several men
drowned when blown into the river.
The last dam block was completed in mid-June, 1934, and the
sluice gates lowered to fill the new lake by September 28.
Work on the powerhouse and installation of the electrical
equipment and generators had proceeded in conjunction with
construction of the main part of the dam.
Installation of the two generators was completed by the end
of 1933, leaving completion of wiring, testing and
commissioning to 1934.
The official opening of the dam took place on October 27,
1934.
Unfortunately, the electrical work had not been completed
and, when Governor-General Lord Bledisloe presided over the
official opening, the symbolic lights were lit with
electricity from Coleridge.
By the beginning of 1935, the power station was operating.
By 1938, it was clear more production was needed and two
additional turbines were installed, one in 1939 and the
second in 1940.
In 1943, electricity demand prompted the installation of a
fifth turbine, to bring the station up to its designed 75mW.
A name, residential address, and (preferably residential) telephone number is required from readers who comment on ODT Online. These details will not be visible to site visitors.