The Opoho Stream culvert is to be reinforced to protect it
from a possible collapse triggered by heavy machinery at
the Forsyth Barr Stadium site in Dunedin. Photo by Peter
McIntosh.
A culvert carrying Opoho Stream under the Forsyth Barr
Stadium construction site in Dunedin is to be reinforced
because of fears it could collapse under the weight of giant
machinery at the site.
Dunedin City Council staff contacted yesterday said they were
seeking confirmation from contractors at the site about steps
to be taken to protect the culvert from collapse.
However, Carisbrook Stadium Trust spokesman Gary Johnson said
the need to protect the culvert had been identified early in
planning for the stadium's construction, and "exceptional
measures" would be taken.
The 337m-long culvert begins at Logan Park and runs
underneath State Highway 88 before crossing under the stadium
site and emptying into the Water of Leith.
Mr Johnson said a temporary brace would be built inside the
culvert to allow a heavy pile-driving rig to drive over it in
the next few weeks.
The rig, which has so far been used to drive piles for the
stadium's south stand, would need to cross the culvert before
beginning work on the north stand piles, which was scheduled
to start in September, he said.
Vibration monitoring equipment would also be installed, and
the weight of machinery crossing the culvert reduced where
possible to minimise stress on the structure, he said.
As construction of the north stand progressed, piles would be
drilled either side of the culvert, with a concrete pad over
the top, to keep weight off the culvert permanently, he said.
"They [contractors] are starting to do the planning around
that," he said.
Earlier yesterday, council water and waste services manager
John Mackie said when contacted he had concerns about moving
an "enormous crane" over the culvert.
"We are certainly concerned about the structural integrity of
the culvert and wanted some assurance from the contractor it
wouldn't fail under the load," he said.
Council water and waste services network manager Rezaul Haque
said the culvert ran between 800mm and 1m below the surface,
which was "not very deep".
He was seeking further information about plans to reinforce
the culvert yesterday.
Mr Johnson said the culvert, along with the rest of the site,
had been surveyed and the subject of engineering reports
early in the planning stages of the stadium project, and
reinforcing work was covered by existing resource consents.
Otago Regional Council director of resource management Selva
Selvarajah said work to repair or maintain the culvert would
be a permitted activity, as long as no permanent change to
the waterway resulted.
- chris.morris@odt.co.nz
Bookmark/Search this post with:
A name, residential address, and (preferably residential) telephone number is required from readers who comment on ODT Online. These details will not be visible to site visitors.