Construction workers pour concrete yesterday for the new
Benmore HVDC link building below the Benmore dam. Photo by
David Bruce.
A huge, white marquee, complete with heating plant,
covered workers yesterday as they embarked on the first major
stage in upgrading the electricity feed from the Benmore dam to
the North Island.
Under it, in work that lasted 11 hours, about 20 construction
workers poured 340cu m of cement - equal to about 70 truck
loads - over 100 tonnes of reinforcing steel, to form the
basement floor for a new four-storey building to house
electrical equipment and a control room for the new "Pole 3"
line.
The Benmore HVDC (high-voltage direct-current) convertor
substation is the southern link in the feed to the Cook
Strait cable and North Island, emerging at the Haywards
substation (in the Hutt Valley, just north of Wellington).
Transpower is spending $672 million at Benmore and Haywards
to increase the HVDC link from its present maximum of 700MW
to 1000MW in 2012 and eventually 1400MW in 2014.
Siemens was awarded part of the contract last year to replace
the 44-year-old Pole 1 equipment at Haywards and Benmore
substations with new, modern thyristor (four-layer
semiconductor) converters.
Preparatory work had already been done at Benmore, but
yesterday marked a major milestone in starting the project,
which is due for commissioning in April, 2012.
Yesterday, between 40 and 50 people in total were on site for
the pouring of the concrete.
At its peak, when electrical equipment starts arriving from
early next year, up to 100 people will work on the upgrade.
They will be accommodated in motels, hotels and rented homes
as far away as Twizel and Kurow.
A mobile batching plant set up on the east bank of the
Otematata River, just off the SH 83 bridge, by Allied
Concrete is producing the concrete for yesterday's pouring
and will remain for future pourings.
Transpower site manager Alan Bulling said a constant stream
of trucks ferried the concrete from the plant to the Benmore
site, where it was fed into a long-reach concrete pump
through an open section of the marquee to be poured to form
the 45m-long, 15m-wide and half-a-metre-deep foundation.
The marquee was needed to protect the fresh concrete from
extreme climatic conditions, such as the heavy frosts the
area can experience.
A heater unit kept the marquee at 12degC ambient temperature
to allow the concrete to cure at a surface temperature of
about 10degC.
Once the concrete had partially set, a team started to float
(smooth off) the surface, which was expected to take until
early today.
The foundation poured yesterday included large reinforced
blocks, which will form part of earthquake proofing allowing
the building to withstand a one-in-2500-year seismic event.
On top of those blocks will go "shock absorbers" (lead-rubber
bearings and sliders), which will allow the building to move
during an earthquake.
Once they are in place, a concrete floor will be laid before
transformers, three new, modern thyristor converters to
convert electricity from alternating current to direct
current - which is more efficient to transmit - a control
room and other equipment are installed.
A new switch station, about half the size of the existing
one, will also be added at Benmore for Pole 3.
The Pole 3 project is a major component of Transpower's wider
investment plan to reinforce the inter-island grid.
The link is critical in balancing energy use between the
islands and will allow for electricity to be transported to
where it is needed, regardless of where it was generated.
david.bruce@odt.co.nz
Bookmark/Search this post with:
A name, residential address, and (preferably residential) telephone number is required from readers who comment on ODT Online. These details will not be visible to site visitors.