Covid-19: Impacts on major projects in Christchurch cost council $6.5m

Contractor claims for changes to the contract of the Ōtakaro Avon River Corridor project have...
Contractor claims for changes to the contract of the Ōtakaro Avon River Corridor project have been finalised. Photo: Supplied
Changes to the delivery of Christchurch's major projects due to Covid-19 have cost the city council about $6.5 million to date.

As of January, 72 per cent of the total claims by contractors of the projects have been finalised.

If a Covid-19 directive leads to a change in the cost to the contractor, it can trigger a variation to the contract, a Christchurch City Council report said.

Additional costs may include demobilisation and remobilisation, site security, direct labour and on-site/off-site overheads.

Variations are reviewed and negotiated between the council and the contractor, and consider factors such as whether the wage subsidy was available for them.

The claims are across 46 projects. Transport makes up 37 per cent, community 2 per cent, and three waters projects make up 61 per cent.

Some of the key projects where claims have been finalised are:

• Pioneer recreation and Sport centre roof replacement

• Ōtakaro Avon River Corridor

• Riccarton Rd bus priority

• St Albans Community Centre

• Opawa Public Library rebuild

• Edmonds Band Rotunda