Plans by Port Otago to scale back how much silt will be
removed during channel-deepening means all of the work can
be done by the port company's own dredge New Era,
pictured at the Kitchener St slipway. Photo by Stephen
Jaquiery.
On the eve of Port Otago beginning its three-week
resource consent application to widen and deepen 13km of the
shipping channel, Senior Reporters Simon Hartley and Rebecca
Fox recap the issues, submissions and process about to get
under way.
Port otago is about to unveil changes to its contentious
proposal to deepen and widen 13km of the shipping channel
from Port Chalmers to Taiaroa Head, scaling back from the
disposal of 7.2 million cubic metres of silt and sand out at
sea to 2.5 million cubic metres.
Of the 195 individuals, groups and businesses who have made
submissions on the proposal, 75%, or 148, are against the
proposal.
Well over 100 submitters - a mix of those for and against -
wanting to be heard and prompting the need for a three-week
hearing; starting on April 4.
While Port Otago will still seek the same resource consents
it originally applied for in May last year, it has extended
the time frame of completing the work from a two-to-15-year
programme out to about 20 years.
Both scenarios ultimately allow for the removal of a total
7.2 million cubic metres of spoil.
The project was initially budgeted at $80 million to $100
million for full deepening and widening to 15m deep, but Port
Otago is scaling back the work into two stages, from dredging
from the existing 13m deep to 15m, and instead going to 14m,
costing an estimated $12 million to $20 million.
Subject to the hearing commissioners granting consent,
dredging work could begin within months.
Initially, it would amount to about 500,000cu m of silt/sand
being removed and dumped at sea over each of the next three
years.
Port Otago has estimated that during the past 145 years, 34
million cubic metres of spoil has been dredged from the
harbour channels.
The change in the plan, while it might allay some concerns
submitters had, was not related to the extent of submissions,
Port Otago's chief executive Geoff Plunket said, but to giant
container shipping operator Maersk, which is Port Otago's
largest customer.
Maersk said in February it now planned to incrementally phase
in ships larger than the present 4100-container carriers,
moving towards 4500- to 5000-carriers in coming years, as
opposed to visits of ships of 6000 containers or more, which
many in the industry had been expecting to occur sooner,
rather than later.
Mr Plunket said deepening from 13m to 14m meant very little
of the channel sides would have to be dredged, but taking
another metre to 15m deep would mean dredging and changing
the profile and sides of the channel.
The company was still seeking the same consent, over a
20-year period, to eventually deepen to 15m, because of the
likelihood container ships will eventually get bigger.
"Given that certainty, at some stage in the future we will
need to go to 15m deep . . . not in 10 years, but within 20
years time," Mr Plunket predicted.
However, given the proximity of the channel near the Aramoana
salt marshes and the potential effects on recreational
fishermen and sportspeople, surfing beaches and avian and
aquatic wildlife, it is expected submitters will continue to
express their environmental concerns, regardless of Port
Otago's time-frame.
For many submitters, the effects of disposal are of most
concern.
A name, residential address, and (preferably residential) telephone number is required from readers who comment on ODT Online. These details will not be visible to site visitors.