A workman can been through one of the first sections of
ETFE that make up the Forsyth Barr Stadium roof. Photo by
Gerard O'Brien
The ethylene tetrafluoroethylene (ETFE) roofing material
that will by April next year cover the Forsyth Barr Stadium is
beginning to be put in place on trusses high above the stadium
site.
The Carisbrook Stadium Trust yesterday gave the Dunedin City
Council an update on the project, including a new time-line,
or "milestone summary", for the construction.
That showed the stadium fit-out was expected to be completed
by June next year, with trials due in July.
The landscaping and plaza was due to be complete by August,
one month before the Rugby World Cup.
Pitch construction was expected to begin this month, "with
acceleration options being reviewed to interface with the
slower-than-expected progress of the structural steel".
Trust chairman Malcolm Farry said last night that meant
because of hold-ups getting steel on to the site, now that
three trusses were in place, work on the pitch would start
while the final two trusses were being put in place, rather
than waiting until they were all up.
The turf work was expected to be completed by April next
year.
Councillors also heard that the recent Christchurch
earthquake, felt in Dunedin, had not affected the stadium.
At a finance and strategy meeting, Mr Farry said while the
time-line had been included in the report, he did not want
councillors to think it was "set in concrete", as there were
variations to the build "almost on a daily basis".
Cr Richard Walls asked where having three of five trusses in
place put the construction programme, and was told by Arrow
International projects director Lale Ieremia the next two
trusses were always to have been put up between now and
Christmas.
The time-line showed the roof structure in place by January
next year.
The "simplistic" answer was there were two to go, and three
months to complete the workThe construction team was now "a
little bit more comfortable" it had time to do the work, even
in the event of bad weather or high winds.
"We've got a little more time," Mr Ieremia said.
Mr Farry said the time-line provided yesterday was "the one
we're working to", and had been provided because of confusion
about the issue in the community "as to whether we're on task
or not".
Cr Chris Staynes asked whether a March-April 2011 finish date
in the time-line for the ETFE roof was critical, and was told
by Mr Ieremia it was, "if we [want to] keep on track".
Cr Kate Wilson asked if there had been any effects on the
stadium from the recent Christchurch earthquake, and was told
by Mr Ieremia there were "none so far".
The stadium was built to withstand a one in 1000-year
earthquake, as Dunedin was considered a "medium-risk" area,
compared to Christchurch, which was low risk.
Asked by Cr Colin Weatherall if he expected problems for
yet-to-be-tendered work, considering the amount of work that
needed to be done in Christchurch would attract contractors
to that city, Mr Ieremia said he did not expect that to
affect the stadium.
A name, residential address, and (preferably residential) telephone number is required from readers who comment on ODT Online. These details will not be visible to site visitors.