The view from the stadium's western end with the south stand to the right and the north to the left. The western and eastern ends provide open space for temporary seating or alternative uses. Photo by Peter McIntosh. |
With less than two months to go until completion, crowds
are again expected to converge on Dunedin's Forsyth Barr
Stadium for today's public open day. Otago Daily Times
reporter Chris Morris and photographer Peter McIntosh skipped
the queue.
It is a long way up from the ground to the roof of the
Forsyth Barr Stadium.
When you stand on the western edge of the grass playing
surface, the stadium's cavernous interior is truly a sight to
behold.
And, after climbing stairs to the highest seat in the
stadium's south stand, your uninterrupted views of the
playing surface down below could easily be those from a
helicopter.
For what has been referred to as a boutique stadium, it seems
both immense and intimate at the same time.
The centrepiece is a lush, dark green paddock of grass,
neatly clipped and waiting, framed by intimidating cliffs of
seating to the north and south.
Claims rugby balls hoofed into the air would be ricocheting
off the roof seem dwarfed by the sheer scale of the project,
capped by the plastic and steel roof soaring high above.
All that is needed is a lick of white paint and some goal
posts, and the "centre bowl" - the playing surface and stands
- will be ready, Carisbrook Stadium Trust chairman Malcolm
Farry, conducting the tour, says.
It is, he says proudly, essentially finished.
As if to underscore the point, a worker in a high-visibility
vest makes his way slowly across the south stand, adding the
finishing touches.
He moves from seat to seat with a brush and shovel in hand,
sweeping each for dust and then moving on.
Other parts of the stadium remain a hive of activity, with
scaffolding smothering the University of Otago building in
front of the stadium's western end, and a pile of material
where the University Plaza landscaping will take shape.
High up on the fourth level of the south stand, two members'
lounges also remain a work in progress.
Sinks lie on the floor, bars and dining facilities are absent
and small piles of building materials are scattered about.
Mr Farry makes no secret of the long hours workers are
putting in each day, or the project managers' seven-day
weeks, to complete the internal fitting out on time.
At the end of it all looms completion date, just seven weeks
away on August 1.
Mr Farry remains as confident as ever about meeting that
deadline, but acknowledges the challenge the two-year
construction project has been.
"I don't want to make it sound easy. There are a lot of
people working very hard to make sure we do complete on
time," he says.
However, he emphasises, come August 1, all signs of
construction will be gone and the stadium ready to impress
all but the most ardent of critics.
"You can't take the smile off our faces, and I have been in
here plenty of times. I still find the experience and the
view quite exhilarating, and I can't wait for it to be full
of people."
The Forsyth Barr Stadium will be open to the public from 11am
until 2pm today. Access will be by gold coin donation, with
proceeds going to the Otago Medical Research Foundation.