Work driving piles into the ground at the Forsyth Barr
Stadium site is going ahead successfully, but the most
difficult stage of the project, lifting about 700 tonnes of
steel roof trusses into place 35m above ground, will be the
major challenge of the project.
"It's a difficult job," Hawkins Construction senior site
manager Dave James said.
In fact, lifting such a weight so high had never been done in
New Zealand before, to Mr James' knowledge.
"It's the first time we've had to lift anything this big this
high," he said.
The lift could take up to seven hours, and require two
400-tonne cranes lifting at once, with pinpoint co-ordination
between them, on a day with no wind.
"You have to plan the timing of it," Mr James said.
If the wind caught the trusses on the way up, the whole lot
could come crashing down.
A visit to the site for an update on construction showed the
work moving steadily ahead.
The piles for the south stand have been sunk in a variety of
configurations, from single piles to some in groups of three
or four, some sunk at angles.
The technique for hammering them into the ground was anything
but subtle.
"It [the pile-driver] sits on top and we start smacking it
[the pile]," said Mr James, who is from Taranaki and has
worked on the Manukau wastewater plant and the America's Cup
wharf, in Auckland.
"We can hammer it in like a nail."
Technology played a part: wires from the piles to a laptop
provided information on their progress when 56 tonnes came
crashing down on top.
Last week, 168 of about 340 piles for the south stand were in
place, although more have been sunk since.
With 150-tonne rigs that were "quite temperamental", the
number sunk per day could vary from 15 to none, Mr James
said.
"So far, we're doing OK."
Most
of the piles were going down 18m, although a "soft spot" on
the quarry side of the site meant piles were closer to 28m,
with one pile spliced on to the top of another when
necessary.
That was expected, and the research done on the pile depths
had proved correct, which was something of a relief,
Carisbrook Stadium Trust development director Darren Burden
said.
"We would have had cost and time problems if that had not
worked; hence the reason we're quite pleased."
The next task was to cap the piles with foundation pads, some
triangular and some rectangular, depending on the number of
piles in a group, which then provided a base on which to
build.
In the meantime, demolition by Hall Bros was still under way,
and as much recycling as possible was being done.
The former Fonterra building will be taken apart, transported
to Marlborough, and rebuilt there.
At another part of the site, a large machine was crushing
concrete, and concrete from an old milk-treatment plant, for
instance, would be used as fill on-site.
About 100 people were working on the site, on the piles and
the demolition, although 250 had been "inducted", and given
safety training.
Numbers would rise to about 500 in six to eight months, when
work on the north, west and south stands was under way.
Once they were built, the roof would go up. The east stand
would be built last.
Up to 60 people would work on steel-work for the roof, which
was being made in Auckland and had to be assembled in
Dunedin.
It was expected the roof would be lifted into place in
January or February next year.
david.loughrey@odt.co.nz
Bookmark/Search this post with:
A name, residential address, and (preferably residential) telephone number is required from readers who comment on ODT Online. These details will not be visible to site visitors.