Meridian Energy Ltd is preparing for a major engineering
feasibility study into its proposed Waitaki River north bank
tunnel power scheme to finalise the design, derive an
up-to-date costing and determine its commercial viability.
A consortium led by Aecom, a professional services company
with offices in more than 100 countries, was selected to
undertake the two-stage study.
It has begun preparatory work already.
Carrying out the full study will depend on issues such as a
decision from the Environment Court on whether water should
be granted for the scheme, a 34km-long tunnel with a single
power house between the Waitaki dam and the Stonewall, near
Ikawai.
There are two options for the power house: underground near
the Waitaki dam or above ground at the outfall.
The study's first stage will look at the viability and
economics of the project, identify a preferred layout and
pursue land-use resource-consent applications with the
Waimate District Council.
The decision to proceed with the study's second stage will be
dependent on the Environment Court's decision and the
viability and economics of the project determined during
stage 1.
If stage 2 goes ahead, it will include further investigation,
an update of cost and risk estimates, and design completion.
The feasibility study is one step in the timetable Meridian
has for the scheme, which could see it completed by 2020.
External relations manager Clare Shaw yesterday said the
study would provide Meridian Energy with a clearer view of
the commercial viability of the north bank scheme.
The information would be used by Meridian managers and the
board of directors to decide if and when to proceed with
detailed design and construction work.
The study would also provide information for the application
for land-use resource consents to build and operate the
scheme.
Expressions of interest in carrying out the study were called
in February and the consortium was now carrying out initial
planning and preparation, she said.
Those processes included some limited drilling and
preliminary engineering design work.
"If and when we commit to a full engineering study, this will
involve more extensive investigations and design work, likely
to take 12 to 14 months," she said.
Some design work and estimates of the cost of the scheme were
carried out by Meridian in a pre-feasibility study to prepare
for resource-consent applications to take water from the
lower Waitaki River.
Meridian made it clear the water-only consents, granted in
December by Environment Canterbury but appealed to the
Environment Court, were just one step in the process of
deciding whether to build the scheme.
Bookmark/Search this post with:
A name, residential address, and (preferably residential) telephone number is required from readers who comment on ODT Online. These details will not be visible to site visitors.