The golden block of George St is chock-a-block with contractors and machinery, as work continues on the next stage of Dunedin’s retail quarter.

The upgrade project began on Monday — earlier than originally planned — and involves replacing and upgrading ageing pipes and then creating a more people-friendly space above, with new paving, street furniture, lighting, plantings and public art.

Starting earlier will allow workers to complete key pedestrian areas ahead of the busy trading period leading into Christmas.



Pedestrian access will be maintained throughout, shops will remain open and car parking is available nearby.

Work in Knox Row is expected to be finished ahead of schedule in June, and the "Malls Block" remains on track to be completed about September.