Australian construction giant CPB will undertake the build, as revealed by the Otago Daily Times in July.
Speaking at the project site Health Minister Simeon Brown described the $1.88 billion project as a "key priority for the Government".
The build is New Zealand’s single biggest health infrastructure project and would provide more than 900 FTE jobs and contribute around $100 million annually to Dunedin’s economy at the peak of construction, he said.

Construction resumed at the former Cadbury site in July, beginning with foundations and pile caps.
A crane will be in the sky mid-next year, with the hospital due for practical completion in 2030 and open to patients in 2031.
In January, after the latest round of delays and a public march by thousands last year, health minister Simeon Brown promised work would resume mid-year.

CPB had expected to sign a contract at the start of 2023, after it had already spent 18 months delivering an Early Contractor Engagement contract (ECE) for the project.
The ECE, signed in August 2021, had required it to plan the build and pull together a team of subcontractors.
For the past two years, the firms have been waiting for a minister to approve the project and CPB has been involved in government discussions about contract details.
CPB has a history of delivering government projects that have resulted in challenges down the track, including rising costs, delays and legal wrangles.
Projects have included the North Island’s Transmission Gully motorway, the Christchurch Hospital acute services building and the Christchurch Parakiore sports centre, which CPB had claimed was costing more than three times as much to build as originally contracted.
In April last year, the ODT unearthed a government briefing about the new Dunedin hospital, from treasury officials to finance minister Nicola Willis, saying HNZ was "reconsidering whether to continue" with CPB on the inpatient build, despite being the preferred contractor.
Since the Treasury note, there have been further delays, including redesigns aimed at achieving savings and even a review of whether the build should go ahead.
Construction timeline and key milestones:
July 2025: Early works commence: Pile caps
August 2025: Preliminary Design complete
October 2025; Developed Design complete
December 2025: Pile Caps complete
January 2026: Detailed Design complete, Substructure commences
July 2026: Structure (Primary Steel) and Base isolators commencement
March 2027: Fitout commencement – floor-by-floor, walls, electrics, plumbing, medical gas, etc
August 2027: Façade commencement
November 2028: Façade finish
Last quarter 2030: Practical completion
First quarter 2031: Go Live / Operational date: NDH open for patients
- The Outpatient Building is expected to reach practical completion in July 2026 and be operational in October 2026.
- Allied Media